How to Live in Your House During a Major Renovation

Written by
Director and licensed builder, QBCC 15280811
Published
Reading time
8 minutes

You can usually stay in your house through a major renovation, but only if the job is staged around three things: one working bathroom at all times, a kitchen you can live without for a defined block of weeks, and a sealed dust barrier between the work zone and the rooms you sleep in. If the roof comes off over your bedrooms, if both bathrooms are out at once, or if the power has to be dead for days rather than hours, you move out for that stage and come back. What homeowners underestimate is not the mess, it is the hours. Sunshine Coast Council sets out the Environmental Protection Act 1994 position plainly: building work must not make noise that is clearly audible from within an affected building between 6.30pm and 6.30am Monday to Saturday, or at any time on Sunday or public holidays. Read that the other way and it allows a lawful 6.30am start, six days a week.

Decide this before you sign, not after the strip-out

Four questions settle whether living in is realistic. Answer them at tender stage, because they change the program and the price.

  • How many bathrooms, and are they on the same drainage stack? One bathroom means you are out for the wet-area stage, or hiring a portable shower and toilet.
  • Is the work above you? Roof replacement, ceiling removal or a second storey over occupied rooms ends most live-in plans: the house is open to weather.
  • Can the services be split? An old switchboard with unmarked circuits, or one water entry with no isolation valve, means every shutdown hits the whole house.
  • Who actually lives there? Shift workers, a baby, anyone with a respiratory condition, or someone on video calls all day, all collide with a 6.30am start.

The staged renovation survival plan

This is the staging we build into the program on live-in renovations. Durations are given as drivers rather than fixed weeks, because the honest answer depends on your scope, your approval and your lead times. Ask your builder for real dates against every row before you commit to staying.

Stage What stops working Where you live, cook and wash What drives the length Sort out before it starts
Site set-up Driveway, garage, side access, part of the yard Normal, but park on the street from day one Fencing, site toilet, skip and temporary power Site boundary agreed in writing, access hours, where the dog goes
Strip-out and demolition The whole work zone, and it is the dirtiest part of the job Sealed living zone, ideally with its own external door Demolition size, hand demolition around retained structure, hazardous material Dust barriers built, ducted air isolated, soft furnishings out
Structural and roof work Weather protection over the affected rooms Book alternative accommodation for this stage Steel fabrication and delivery, engineer inspections, weather Somewhere to go, contents out of the rooms below, temporary roofing plan
Services rough-in Power and water in blocks, not all day every day Stay, with notice-based shutdowns Circuit and fixture counts, notifiable plumbing work, inspections A written shutdown schedule, devices charged, drinking water on hand
Kitchen out Cooking, sink, dishwasher, usually the fridge position Temporary kitchen in the laundry, dining room or garage Cabinetry manufacture, benchtop templating after cabinets land, appliances Bench, microwave, kettle, a usable sink, laundry tub protected
Bathroom out One or both wet areas Second bathroom, or hired shower and toilet Screeds and waterproofing curing before tiling, tile and tapware supply Shower roster, waterproofer and tiler booked in sequence
Linings, floors and paint Traffic through finished areas, sometimes the whole floor plate Stay, but living around no-go zones Set and sanding cycles, paint recoat and floor coating cure times Ventilation plan, a route in that never crosses fresh coatings
Fit-off and handover Little, but trades are in and out constantly Back to normal, in stages Deliveries, final inspections, defect rectification Your defects list started early, not on handover day

Dust control: what good actually looks like

In our experience it is dust, not noise, that pushes people out of the house. Plastic taped across a doorway is not dust control. What works is a barrier built like a wall: stud or zip-wall partitions sealed at floor and ceiling, a proper zipper door, a tacky mat at the threshold. Ducted air conditioning gets shut down and every return in the work zone sealed, because ductwork spreads demolition dust through the whole house in an afternoon. Cutting tools run on-tool extraction into an H-class dust extractor, not a workshop vac. Living-zone floors get protection board, not a drop sheet, and the daily clean-down goes in the program rather than being left to goodwill.

If there is any chance of asbestos-containing material in linings, eaves, sheeting or old floor coverings, it is identified and dealt with under Queensland’s work health and safety laws before anything is cut or drilled. Your builder settles that before strip-out, not on the day with the saw already running.

Services isolation: who is allowed to touch what

Ask for a written shutdown schedule, because “the water is off tomorrow” is not a plan when you have kids to get to school. You want the day, the start time and the expected restoration time for every isolation, a week ahead.

Plumbing isolations are not informal. The QBCC lists twelve categories of notifiable work in schedule 1 of the Plumbing and Drainage Regulation 2019, including installing or relocating a fixture, and installing, replacing or removing a water heater. The licensed plumber has to identify which of those categories the work falls under when completing a QBCC Form 4/4a. Ask for those records at handover.

While ceilings are open, deal with smoke alarms. The Queensland Government requires all existing private homes, townhouses and units to have interconnected photoelectric smoke alarms by 1 January 2027, complying with Australian Standard 3786-2014. Doing it while the linings are off avoids the later job of cutting, re-cabling and patching finished plasterboard room by room.

Noise, access and the neighbours

Sunshine Coast Council states that under the Environmental Protection Act 1994 building work must not make noise that is clearly audible from within an affected building between 6.30pm and 6.30am Monday to Saturday, or at any time on Sunday or public holidays, and that working outside those hours requires a permit application under Local Law 1 (Administration) 2011. The Act is state legislation, so the same hours frame jobs in Noosa Shire; for out-of-hours work there, check the permit process with Noosa Shire Council.

Then agree three things in writing: which door the trades use, where they park, and whether anyone enters the occupied zone without notice. On a live-in job that last answer is no, except in an emergency.

The contract terms that matter when you live on site

The QBCC requires a written contract for domestic building work priced over $3,300 including labour, materials and GST, using a Level 1 Renovation, Extension and Repair Contract for $3,301 to $19,999 and a Level 2 contract for $20,000 and over. Most residential building work valued at more than $3,300 must also be covered by the Queensland Home Warranty Scheme, which the QBCC describes as covering a maximum of $200,000 each for various conditions, with optional additional cover available.

Variations matter more when you live on site, because you are standing there when the wall opens up. The QBCC requires the contractor to present the variation in writing and the owner to agree in writing before the variation work starts, with a written copy given to you before the domestic building part of that work starts or within five business days of both parties agreeing, whichever happens first, and states you cannot be required to pay for a variation before the variation work is started. The QBCC allows one exception, where the work has to be carried out urgently and producing a written copy first is not reasonably practicable. Read how variations work in Queensland before agreeing to anything scribbled on a plan.

Insurance is the clause people skip. The QBCC advises discussing insurance responsibilities before signing, says contract works insurance covers the site and materials against theft, vandalism, fire and storm, and points out you could be required under the contract to take out public liability insurance. Ring your own home and contents insurer too: policies differ on cover while a house is under construction and partly occupied.

When staying is the wrong call

Move out when the roof is off over occupied rooms, when your only bathroom is being waterproofed, when the house is being fully rewired or replumbed, or when someone in the household has a respiratory condition. Weigh the hidden cost too: a live-in program means sequenced zones instead of the whole floor plate, daily protection and clean-down, and return visits to the same rooms. That is real time and money in the tender, and on some jobs a short rental works out cheaper than months of staged access. If it is close, read the renovate or knock-down-rebuild comparison as well.

We stage this on every job, from the Kara Court renovation at Yaroomba to the Grandview Drive project at Coolum Beach, which won three Master Builders Queensland 2025 Sunshine Coast Housing and Construction Awards. To have the staging worked out before you decide, talk to our Sunshine Coast renovation team.

Frequently asked questions

How long will my kitchen be out of action?

Longer than the demolition suggests. The clock is driven by cabinetry manufacture, benchtop templating that can only happen once the cabinets are installed, stone fabrication and appliance lead times. Get the cabinetmaker’s booked delivery date before you set up the temporary kitchen. Our kitchen renovation cost guide covers the budget drivers.

Can I keep using one bathroom while the other is renovated?

Usually, if they are on separate drainage and the isolation valves hold. The stage you cannot rush is waterproofing: membranes installed to AS 3740, Waterproofing of domestic wet areas, have to be applied in the specified coats and left to cure before tiling starts. See the bathroom renovation cost guide for the sequence.

Can the builder really start at 6.30am?

Yes. Sunshine Coast Council states that the restriction on building work noise clearly audible from within an affected building runs 6.30pm to 6.30am Monday to Saturday, and all day Sunday and public holidays, under the Environmental Protection Act 1994. If that does not suit your household, negotiate a later start into the contract rather than assuming one.

Who is responsible for security while the house is open?

Check the contract. The QBCC says contract works insurance covers the site and materials against theft, vandalism, fire and storm, but your personal contents are separate. Move anything valuable out of the work zone before strip-out and lock the occupied zone from the inside.