What shapes a bathroom renovation
Why the membrane comes first
Waterproofing defects show up consistently in the QBCC top ten list of defective work complaints. That is why we treat the membrane as a hold point: it is inspected before the tiler starts, and we photograph it so you have a record.
The standard wet areas are built to
We rebuild wet areas to AS 3740:2021, the standard NCC 2022 references. No part of the shower floor may be left unprotected, hobs and step-downs included, and the wall membrane runs up to at least 1800 mm. These provisions have applied in Queensland since 1 May 2023, and NCC 2022 continues to apply here because NCC 2025 has been delayed in Queensland until 1 May 2027.
Air as well as water
NCC 2022 Housing Provisions set an exhaust rate of 25 L/s for a bathroom, discharged to outdoor air directly or through a duct. Where the room is not naturally ventilated, the fan is interlocked with the light switch and keeps running for 10 minutes after the light goes off.
How we run the job
We settle the layout, fittings and finishes with you first, then book trades in a fixed order around them. Plumbing rough-in, membrane, tiling and fit-off each get checked before the next trade arrives.
Sources: QBCC: Waterproofing done right, what you need to know (2025), NCC 2022 Housing Provisions Part 10.8 Condensation management